Pump checklist

A pump checklist grouped by frequency, covering seals, valves, bearings, alignment, and guards, with the bearing regrease by running hours.

Daily

TaskRequiredPhoto required
Before work
Before service, lock out power, isolate the pump, and relieve the pressure. Never heat an impeller to remove it.RequiredNo photo required
Inspect
Check the overall condition, and that the coupling guard is in place. Never run the pump without it.RequiredNo photo required
Check the seal or packing for leaks. Photograph any leak found.RequiredNo photo required
Check that the suction and discharge valves are open. Never run the pump at shut-off or below its minimum flow.RequiredNo photo required
Check that bearing temperature, vibration, and noise are normal.RequiredPhoto required
Switch off or sequence the pumps that are not needed.Not requiredNo photo required

Monthly

TaskRequiredPhoto required
Before work
Before service, lock out power, isolate the pump, and relieve the pressure. Never heat an impeller to remove it.RequiredNo photo required
Lubrication and packing
Lubricate bearings to the manufacturer's recommendation.RequiredNo photo required
Check the packing for wear, and repack as needed.RequiredNo photo required
Alignment and mounting
Check pump and motor alignment.RequiredNo photo required
Check that the mountings are secure.RequiredNo photo required
Power transmission
Inspect belts, pulleys, and couplings, and keep them in good working condition.RequiredNo photo required
Standby
For a pump in storage or extended shutdown, turn the shaft by hand 10 to 15 turns.Not requiredNo photo required

By running hours

TaskRequiredPhoto required
Before work
Before service, lock out power, isolate the pump, and relieve the pressure. Never heat an impeller to remove it.RequiredNo photo required
Lubrication
Regrease the bearings at the interval the manufacturer gives. Shorten it in dirty or wet conditions, or where the ambient or bearing frame runs hot.RequiredNo photo required

After a change or service

TaskRequiredPhoto required
Before work
Before service, lock out power, isolate the pump, and relieve the pressure. Never heat an impeller to remove it.RequiredNo photo required
Alignment
Recheck alignment after a process-temperature change, a piping change, or service.RequiredNo photo required

Annual

TaskRequiredPhoto required
Before work
Before service, lock out power, isolate the pump, and relieve the pressure. Never heat an impeller to remove it.RequiredNo photo required
Wear and condition
Inspect bearings and drive belts for wear.RequiredNo photo required
Check motor condition by temperature or vibration analysis.Not requiredPhoto required

Import it into FixAhead

Upload this file in FixAhead's maintenance procedure import, as a signed-in owner or manager. Each frequency loads as its own procedure, with its sections, tasks, and each task's Required and Photo required marks. If your account already has a procedure with the same name, this one is skipped and the existing one stays as it is.

Maintenance procedures are on the Pro plan, as pricing shows.

Ready to get ahead of breakdowns?

Start free. No credit card required.